Update by Bethany Oakley
Good afternoon,
I hope you are well.
Before we leave for the Christmas Break, I wanted to share some great progress with you, that the Team on Site have continued to deliver.
- The new MCC kiosk has been installed
- JHT attended to fit the steel grate flooring inside the MCC and they also installed the new balance tank.
- O’Connor Utilities came in to install the new mains cable for the site On Friday 13th December.
- Intelect attended to in pull in the cables
- The surround to the PS Tank and inlet manhole has now been concreted.
- We have built up most of the draw pits with brickwork and started installing the new lids.
In the event that you require some assistance in our absence during the Christmas Break, please contact 0345 7171100
We wish you a Merry Christmas and a Happy and Healthy 2025.
Take care,
Bethany