The construction phase of this project is now complete.

There may still be updates, so the project will remain here. We are still monitoring the project and will reply to any comments. So if you have any questions please feel free to comment or contact us here.

GENERAL PROJECT
CURRENT WEATHER
0°C

Escomb Rising Main

Project to replace a failing pumping main from Escomb Pumping Station to Etherley Moor.

Project updates

Update by Sarah Jayne Parvin

Good afternoon, there are some repair works we need to carry out on the foot path between Etherley Lane and the fields. 

This work will be carried out on Thursday 19th and Friday 20th September and will be reopened on the afternoon of the 20th, please use alternative access untill then.

Any questions please comment below or use the 'countact us' at the top of this page.

Thanks 

Sarah 

Please Login in order to comment on this update.

Update by Sarah Jayne Parvin

Good afternoon, we just wanted to share with you some of the community work we have done in the area earlier in the year. Throughout our project Weardale Railway have been nothing but accommodating especially when we carried out our work across the footbridge. We decide to say thank you and give something back to them. Several members of the project team (MMB Sarah Jayne Vickers, Will Brown, Jessisca Merrit, Gaby Ward, Rob Anderson, Pat Corris, NWG Peter Greenan and Turner and Townsend Leila Tunstall) who all volunteered to paint the fence at Bishop Auckland West stand. We were really grateful that the rain held off, it did threaten to rain a number of times! There was even time for a coffee and donut break, well deserved for everyone involved. I have included a few photos below of the day.

Thanks

Please Login in order to comment on this update.

Update by Sarah Jayne Parvin

Good afternoon everyone, we just wanted to provide you with an update as you will have realised our works are nearing completion.

This project involved replacing the failing pumping main pipe from Escomb Pumping Station to Etherley Moor.  This pipe has suffered several bursts since 2006 due to pipe’s age and condition. The new pipeline route is just under 1 mile (1.4km) in length and follows the existing Public footpath, which is now in situ and in service. We have a few outstanding things to complete over the next week or so, which involve erecting fencing around the land we occupied for the site compound and tidying of the area.

Ill follow this up with a further update once we have completed the finishing touches. 

We would like to thank everyone for their patience during our works.

Thanks

Sarah Vickers

Please Login in order to comment on this update.

Update by Sarah Jayne Parvin

Good morning, a quick update to let you know that the traffic management has been removed yesterday from Etherley Moor Lane. No further traffic manaement is expected. Last week i was asked about the footpath and i advised we were constructing a manhole within the footpath. We expect the foot path will reopen in March.

I have included some pictures below to show the 100mm ductile iron pipework installed under the iron footbridge to carry new sewer across weardale railway, the pipe is hung from the wooden joists to preserve the listed ironwork bridge structure.

Thank you for your patience, and as always any questions please us the contact us at the top of the page.

Sarah

Please Login in order to comment on this update.

Update by Sarah Jayne Parvin

Good morning, further on from my previous update re the traffic management. It has been decided, due to unforeseen circumstances to close the road. This closure will run between the hours of 9.30 and 3pm on the 7th February. During this time a diversion will be put in place, I have included a map below to show the route.

Thank you for your patience.

Sarah 

Please Login in order to comment on this update.

Update by Sarah Jayne Parvin

Good afternoon Everyone, time for an update of where we are now and how long we can expect this to take.

You may have notice already we have some traffic management in operation at Etherley Moor, and we envisage this to be in place till the 15th Feb.

This is so we can tie in the new rising main into the main that runs down Etherley Moor, due to the amount of unmarked services in the ground, the vast majority of this will be dug by hand.

We apologise for any inconvenience this will cause.

If you have any questions or concerns please don’t hesitate to contact us, using the contact option at the top of this page.

Regards

Sarah Vickers

Please Login in order to comment on this update.

Update by Sarah Jayne Parvin

Good morning All, Happy New Year and hope you all enjoyed the festive holidays.

Quick update to keep you all in the loop of what we have been up to and what we have planned over the coming weeks. 

All the directional drilling works (trench-less excavation) have been completed and tested. For us to carry out the directional drilling we need to dig out Launch and reception pits, these are large excavations where we start the drilling and where we are drilling the pipe through to, which are all now backfilled.

Over the coming weeks we are installing the scaffolding to the bridge, which will allow us to install the pipework to the underside of the bridge. This will then be followed by painting the pipe, connecting the pipe and carrying out pressure testing.

The most important thing to add all this work is carried out to the highest safety standards with the public and work force always front of mind.

We would like to thank you all for your patience! As always if you have any questions please use the contact us function at the top of the page.

Thanks 

Sarahjayne 

Please Login in order to comment on this update.

Update by Sarah Jayne Parvin

With the Christmas Holidays coming up, it’s time to share our final post of the year!
We would just like to thank all our lovely customers for their continued support and cooperation throughout the year to allow our projects across the region to run as smoothly and quickly as possible. Our sites will be shutting down on Friday 21st December and will re-open Thursday 3rd January. For anything urgent, you can contact the 24-hour Customer Contact team at Northumbrian Water on 03457171100.
From all of us at MMB, we wish you all a Merry Christmas, and a very Happy New Year!

Please Login in order to comment on this update.

Update by Sarah Jayne Parvin

Good evening all, I would like to make you aware that we are closing the foot path behind Beckett Close, I have attached a map below and highlighted the section. The closure will be first thing tomorrow morning and all being well, reopened on Wednesday. 

Thank you for your patience. 

Sarah Vickers MMB

 

Please Login in order to comment on this update.

Update by Sarah Jayne Parvin

Good afternoon Everyone, I would like to provide you with an update as to what we have been up to and what we have planned up until we break up for Christmas on the 21st December.

The Open trench works south of the railway are progressing well despite the weather over the last week or so, we are approximately 25% complete on this section of our project. We have opted to directional drill (horizontal wells) the lower section of the pipe line to cause minimal disruption to the land owners, this section up to the railway will be complete by Christmas.

In the new year we will erect scaffolding under the railway footbridge to allow us access to install the new pipe under the bridge deck.

If you have any questions please dont hesitate to contact us using the 'contact us' button at the top of the page.

Please Login in order to comment on this update.

Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers