Esh Winning STW – Chemical Removal

We are investing £4m to improve the performance of our sewage treatment works at Esh Winning STW. The work will involve the installation of new equipment which will provide additional chemical removal before the final effluent is discharged. This will aid NWL in improving the quality of rivers and coastal waters for the benefit of people, the environment and wildlife.

Project updates

Update by Alice Blackett

Good afternoon all,

We wanted to take this opportunity to provide the last update of the year!

Our last working day is Friday 20 December 2024 for the Christmas and New Year period and will return to work on Monday 6 January 2025. 

We wish all our customers a Merry Christmas and all the very best for 2025.  We would also like to thank you all for your patience and understanding whilst we have carried out our works.

If you have any concerns over the Christmas and New Year period, please contact us by emailing nwl.customer@esh.uk.com.

Merry Christmas to you all, stay safe and wrap up warm!

Thank you 

Rachel, Alice and Christine.

Please Login in order to comment on this update.

Update by Alice Blackett

Good Morning

A little update on our Esh Winning Sewage Treatment Works.

Our team have been working really hard on the lead up to Christmas and have been carrying out general reinstatement works, installed the delivery slab and have now started the electrical install.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com

Please Login in order to comment on this update.

Update by Alice Blackett

Good Morning

Works are progressing and we are currently installing ducts for the chemical dosing lines.

A road closure will be in place on the B6302 from 8pm Sunday 6th October - 6am Monday 7th October whilst the site team take safe delivery of materials.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com

Please Login in order to comment on this update.

Update by Alice Blackett

Good Morning

I hope you are all well.

Since starting on site, we have made good progress with works all going to plan.

The welfare and offices are all set up, and we have cast the concrete slabs for the chemical dosing kiosks and started the duct work around the site.

Over the next few weeks, we'll be continuing to install ducts for the chemical hoses and electrical cables.

Please refer to the photographs to see the progress.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com

Please Login in order to comment on this update.

Update by Jamie Oyebade

Good Afternoon,

Hope you are well?

I wanted to give you an update as to how we are progressing with the survey work at the site.

We have completed drone, topographical and GPR surveys of Esh Winning STW which, when we receive the results, we will be able to use to model the existing works and to aide our design.

The Ground Investigation (GI) survey will commence on 25th September 2023. This will involve digging a series of boreholes and trial pits as well as taking samples to be assessed at the laboratory allow us to understand the ground conditions at the treatment works. 

Please feel free to leave a comment below should you have any questions or even if you just wanted to say hello, we will be more than happy to help.

On behalf of the project team, we are looking forward to working in your area.

Kind Regards

Jamie

Please Login in order to comment on this update.

Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers