Update by Alice Blackett
Good Morning
I hope you are all well.
Since starting on site, we have made good progress with works all going to plan.
The welfare and offices are all set up, and we have cast the concrete slabs for the chemical dosing kiosks and started the duct work around the site.
Over the next few weeks, we'll be continuing to install ducts for the chemical hoses and electrical cables.
Please refer to the photographs to see the progress.
Please contact us direct if you have any questions at nwl.customer@esh.uk.com