Update by Julie Oakley
Good morning, Everyone,
hope you are all looking forward to the lighter nights and warmer weather.
I thought it was that time of the month to provide you with an update on the progress we have made here on Felton treatment works. We have now installed the second new screen for the inlet works, we are also progressing with the installation of the pumps and pipework for the Humus settlement tank (HST) desludge slab which is the secondary treatment process and the new penstocks have been completed successfully, along with the flowmeter and pipework which controls the water flow.
I would like to thank you all for your continued patience while the works continue but if you have any issues or queries please leave a comment below or use the details provided to contact us and one of the team will be happy to help.
thanks
Julie