Hello. We have made steady progress on site since the last update on the Fontburn project. We have progressed the design detail and continued operations at several locations on site.
The temporary crane platforms are complete and advance works to remove the first of the silos have started.
We will start working in the pre-lime chamber and in the waste water building. The planning stage is at an advance stage.
The next operations are to continue with the pre-accommodation works.
The site and compound set-up are complete. The works areas comply with the covid management protocols. The Project supports "the three simple actions" promoted by the NHS; "wash hands, cover face and make space"