Update by Shafqat Akbar
Hello everyone. In today's update, I want to tell you about the good progress we have made on the installation of the two new lime silos.
The first new silo has been installed. We carried out the works while the treatment works remained operational. Our site teams are now fitting the pipelines, electrical cables and chemical lines to the silo.
The site teams will commission the first silo after the installation works are complete. The second silo will be transported to site and installed in the next phase of the works.
We have carried out all of the works on site without affecting the day to day operations of the treatment works. We have agreed a programme of works that allows us to construct the lime dosing infrastructure and Northumbrian Water to maintain the water supplies.
Our site teams will be connecting the new lime silo to the existing treatment plant after the commissioning works are complete. Works are progressing well and we will be arranging delivery for the second new silo shortly.