Update by Christine Taylor
Good morning,
I have managed to catch up with the team for an update.
They have advised that they have completed the installation of the Legato blocks and geogrid earth reinforcement. The embankment drainage is now also complete the earthworks fill to the embankment is progressing well. They have also installed the impermeable beck channel liner ready to reinstate Car Beck.
The team have sent over photos to provide a visual of the works completed.
Christine