Update by Simon Cossar
Good morning all,
Just an update following our customer visit on the 11th January 2023 and developments since then,
We now have a revised draft programme for the install of the booster following the delays before Christmas.
We are planning to install the new booster starting week commencing Monday 13th February 2023. The work is likely to take approximately a week to install and test, once compete we will run on the new booster for a period to prove it works fine and we get confidence in its operation. We will then look to remove the old one (which we will still be able to revert back to if we experience any problems during the proving period.)
There is a possibility you will see a few fluctuations in your water pressure during this period but we will be trying our best to keep this risk to the bare minimum.
You may see activity on site before these dates while we prepare the site for the works, and I will confirm once these dates are set in stone.