GENERAL PROJECT

Great Broughton Sewage Treatment Works

At Northumbrian Water, looking after the environment is one of our top priorities. As part of this commitment, we are working with our supply partner, Mott MacDonald Bentley to undertake upgrade work at Great Broughton Sewage Treatment Works (STW) to improve the performance of our wastewater treatment. This essential work will help to improve water quality and ensure that the treatment facility continues to serve the community effectively.

Update by Bethany Oakley

Good afternoon all,

I hope you’re well.

Before we leave for the Christmas Break, I wanted to share a final update on the Great Broughton Sewage Treatment works. The Team have been continuing with their progress and this is an excellent end to the year.

  • Rising main pump plinth 2 reinforcement installed and concrete has been poured.
  • Rising main 2 Stainless Steel suction pipework installed
  • Rising main 1 Stainless Steel inlet pipework installed
  • Storm tank footpath and aco drainage constructed.
  • Inlet channel cored through to confirm reinforcement depth, good news no change to our current design required.
  • Prepped road and chambers ready for final road pour this week.

In the event that you require some assistance in our absence during the Christmas Break, please contact 0345 7171100

We wish you a Merry Christmas and a Happy and Healthy 2025.

Take care,

Bethany

 

Please Login in order to comment on this update.

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers