Update by Bethany Oakley
Good morning,
I hope you’re well and enjoying the week so far.
Now that we are nearing completion of the Great Broughton STW Upgrade, I wanted to provide an update on the progress we have made:
All major components have now been installed, tested and commissioned with only minor elements of the work remaining; these will be completed within the next few weeks.
Our office and Site welfare cabins have been downsized and replaced with a single welfare unit, reflecting the small amount of work remaining.
Should you have any questions regarding the works, please don’t hesitate to add a comment in the box below and a member of the Project Team will respond accordingly.
Best Regards,
Bethany.