The construction phase of this project is now complete.

There may still be updates, so the project will remain here. We are still monitoring the project and will reply to any comments. So if you have any questions please feel free to comment or contact us here.

WATER NETWORK IMPROVEMENT
CURRENT WEATHER
12°C

Greenwood Road, Billingham, Mains Renewal

Description of Project Our contractors Fastflow will be carrying the construction of a new HPPE water main to replace 1000m of the existing 16" UPVC water main. This will be done using trenchless techniques where possible to minimise disruption.

Planned Work

NWG want to let you know details of essential work we will be carrying out in Greenwood Road to renew and replace 1000 metres of UPVC water mains with new plastic water mains. You may be aware that we have recently experienced bursts in this area and essential work is required to replace this section of pipework.

What are we planning and when

Our experienced contractors, Fastflow Pipeline Services are carrying out this work on our behalf. This will involve the construction of a new water main along Greenwood Road from the junction of Cowpen Lane to the B1275 roundabout. Work will begin on Monday 9 April 2018 and we expect to complete by Friday 15 June 2018.

Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers