The construction phase of this project is now complete.

There may still be updates, so the project will remain here. We are still monitoring the project and will reply to any comments. So if you have any questions please feel free to comment or contact us here.

GENERAL PROJECT

Hexham STW Refurbishment

We are investing over £4.9 million to improve Hexham Sewage Treatment Works. This investment is being undertaken to address asset condition and performance concerns meeting the demands of the upstream drainage catchment. Undertaking this refurbishment work will improve the sites compliance resilience, reducing the likelihood of future pollution incidents, minimising operator intervention improving site Health & Safety. Our sewage treatment works aids NWL in improving the quality of rivers and coastal waters for the benefit of people, the environment and wildlife.

Project updates

Update by Dave Eden

Morning All.

Let’s get up to speed on the Hexham STW Refurbishment:

The seeding of the new filter beds is continuing, but unfortunately the first set of external biological samples weren’t quite up to spec, so we’ll continue the process for a while longer. Further samples will be taken this week, with results available the back end of the week after.

The inlet works area is continuing – in addition to the main inlet screens slab we have now completed the MCC slab, the wash-water booster slab and all the ducts and draw pits bar a little tweaking.

Coring into the existing balancing tank has restarted and is hoped to complete by the end of the week despite some minor teething issues.

Installation of the super-structure of the inlet works is still planned to commence early June, but the final epoxy coating of the re-furbished distribution chamber has been re-arranged for a later date due to the ongoing seeding.

Thanks.

Dave Eden

Please Login in order to comment on this update.

Update by Dave Eden

Morning All.

Time for another Hexham STW Refurbishment update:

The seeding of the new filter beds is continuing, and the samples continue to look promising. We have had some external sampling carried out and await the results.

The inlet works area is progressing well, with most of the ducts and draw-pits in place and the MCC slab, Wash water booster slab and flow meter chamber underway.

Coring into the existing balancing tank is currently on hold due to some tooling issues but is programmed to re-start 20/05/24.

Assuming all goes well we will be looking to start the super-structure of the inlet works in early June and also complete the final epoxy coating of the re-furbished distribution chamber around th same time.

Thanks for taking the time to read through the update. There is some further information in and with the photos.

Please Login in order to comment on this update.

Update by Dave Eden

Morning All.

Time for another Hexham STW Refurbishment update:

The seeding of the new filter beds is continuing well, with biological sampling results suggesting they will be mature well ahead of schedule.

We are continuing civils works on the inlet works area, currently installing all the remaining ducting and pipework ahead of constructing the 3 remaining base slabs.

We have commenced the works to core into the existing balancing tank with the wall plate now bolted to the wall of the chamber ready for pressure testing before the valve is installed ready for coring to begin. This core will allow us to divert the flows into the new inlet works once they are complete.

The refurbishment of the existing Detritor and grit rake is nearing completion. The equipment is all back in place and electrically connected with a view to bring it back into operation this week.

That's all for now, but as always, there's more information in the photos.

Please Login in order to comment on this update.

Update by Dave Eden

Time for another Hexham STW Refurb update:

The over pumping is now in place to recirculate the flows coming through the new filters into the old filters so that the wastewater is fully treated whilst the new filters are seeded. This process could take 4-5 months but given the warming weather we hope the bug will establish themselves much sooner.

The structural repairs to the Detritor are complete and we are looking to reinstall the refurbished grit rake 1st May and commission the entire kit soon after.

Masonry repairs to the distribution chamber have been completed. Helical bars were grouted into the mortar between the bricks to tie the whole structure together and reinforce areas of cracking then the whole structure was repointed.

Looking forward we’ll turn our attention back to the inlet works area, installing further ductwork and slabs for the MCC, compactor and wash water booster. We will also core into the existing balancing tank for future connection to the new inlet works.

Thanks for taking the time to read and have a look at the attached photos for further information.

Dave Eden PM

Please Login in order to comment on this update.

Update by Dave Eden

Hi everyone,

 

Time for another update for Hexham STW Refurbishment:

The work to refurbish the existing Detritor and Grit Rake has hit a snag when we have found some structural significant cracking in the ground structure around a mounting point which will take considerable force. We’ll be removing the grit rake again to carry out some concrete repairs in the near future.

We are continuing to install new Ts on the pipework around the distribution chamber to allow the filters to be operated without using the distribution chamber if and when necessary. Three of the four are mostly complete.

We have pushed the seeding/over-pumping back a week to allow for the T’s to be completed and some tweaks to the set up of the pumps now that they have to share room with the T’s.

The new inlet screens slab has been blinded out ready for the Formwork, Reinforcement and Concrete (FRC) sub-contractor who started preparing shuttering today.

 

As mentioned previously, the continuing traffic management outside the site is not part of our works and is controlled by another contractor - emergency numbers should be displayed on the traffic management signage.

 

I’ve attached a few photos to illustrate progress on site.

Thanks for taking the time to read the update.

 

Dave Eden, Project Manager

Please Login in order to comment on this update.

Update by Dave Eden

Hi everyone,

 

Spring has sprung and we’re still moving forward with the refurbishment at Hexham STW.

Works to repair and re-waterproof the existing distribution chamber have reached a point where the chamber can be brought back into use rather than relying on expensive temporary pumps. The final epoxy coating is still to be done, but this requires a number of consecutive dry days so we will come back to that later in the year.

The Detritor is being reinstalled as I type, though the whole process will take a couple of weeks. Anyone nearby may be able to see the crane lifting the newly refurbished and re-painted pieces into place.

Work at Peth Head SPS to alter the pump set up and thereby smooth out the flows was completed last week. This should make the STW run more efficiently by providing more constant flows into the site rather than stop/start.

Construction of the 2nd recirculation manhole is complete ready for the seeding of the new filter which is expected to start WC01/04/24. The seeding could take up to 20 weeks, but it is hoped to be complete much sooner.

Work on the new inlet works is also underway. We have excavated down and broken out some old concrete structures, installed ducting and stoned up ready for blinding concrete by the end of the week and formwork reinforcement and concreting to start in the near future.

 

As mentioned previously, the continuing traffic management outside the site is not part of our works and is controlled by another contractor - emergency numbers should be displayed on the traffic management signage.

 

I’ve attached a few photos to illustrate progress on site.

Thanks for taking the time to read the update.

 

Dave Eden, Project Manager

Please Login in order to comment on this update.

Update by Dave Eden

Hi everyone,

 

Works are progressing well at Hexham STW Refurbishment, especially now we are getting extended periods of fine weather.

Works to repair and re-waterproof the existing distribution chamber are going well, with some extra labour on site and weekend working to try to get complete while the weather hold. All the repair and much of the waterproofing is finished and we will hopefully be applying the final epoxy layer next week.

We are also busy installing some Ts on the distribution pipework which will allow the filters to be operated without using the distribution chamber should it require further works in the future.

The Detritor continues to be refurbished offsite but is expected to be reinstalled WC 18/03/24.

Work has begun over at Peth Head SPS to alter the pump set up and thereby smooth out the flows coming into Hexham STW. This should take around 2 weeks.

 

Construction of the second recirculation manhole has been put on the back burner until the T’s are in place because we need either the Ts or the distribution chamber complete before we can begin the recirculation.

 

As mentioned previously, the continuing traffic management outside the site is not part of our works and is controlled by another contractor - emergency numbers should be displayed on the traffic management signage.

 

Thanks for taking the time to read the update. Please have a look at the attached photos for some more detail.

 

Dave Eden, Project Manager

Please Login in order to comment on this update.

Update by Dave Eden

Hi everyone,

 

Works are progressing at Hexham STW Refurbishment though the wet weather continues to provide challenges.

Works to extend the water main to the intended location of the new inlet works are complete as much as possible until the new inlet works is under construction.

The Detritor continues to be refurbished offsite and is expected to be away around 3 more weeks.

Works to repair and re-waterproof the existing distribution chamber are continuing and will take up to 4 more weeks depending on weather and flow issues.

I am pleased to say the distribution columns and arms on the new filters are in place, meaning the filters are structurally complete and ready for seeding.

Construction of the second recirculation manhole is underway. On completion of this manhole and the waterproofing works to the distribution chamber, we will be able to start passing flows through the new filter beds, which will gradually bring them into operation over a number of weeks.

Looking ahead, the electrical alterations to improve the operation of Peth Head SPS pumping into Hexham STW is now expected to commence in a week or two and ground works for the new inlet works at the STW are imminent.

 

As mentioned previously, the continuing traffic management outside the site is not part of our works and is controlled by another contractor - emergency numbers should be displayed on the traffic management signage.

 

Thanks for taking the time to read the update. I have also attached photos to illustrate.

 

Dave Eden

Project Manager

Please Login in order to comment on this update.

Update by Dave Eden

Hi everyone,

 

We are progressing well at Hexham STW Refurbishment despite the extremely poor weather causing some issues.

Works to extend the water main to the intended location of the new inlet works are continuing intermittently along the internal site road.

The Detritor removal was completed and is being refurbished offsite and is expected to be away around 6 more weeks.

Works to repair and re-waterproof the existing distribution chamber have commenced and are expected to take 4-6 weeks.

Installation of the distribution arms on the new filters should start next week.

When the arms and the waterproofing works are complete, we can start to seed the new filter beds to bring them into operation of the course of a number of weeks.

We are also starting to look at works at Peth Head Sewage Pumping Station which needs minor adjustments to go along with the main works at Hexham STW to make the flows more efficient.

 

Please note that the traffic management outside the site is not part of our works and is controlled by another contractor - emergency numbers should be displayed on the traffic management signage.

 

Thanks for taking the time to read the update. I have also attached photos to illustrate.

 

Dave Eden

Project Manager

Please Login in order to comment on this update.

Update by Dave Eden

Morning All and Happy New Year.

 

We have returned to work at Hexham STW Refurbishment after our hard-earned break.

After the unavoidable delay of remobilising plant and equipment back to site we have made good progress:

Works to extend the water main to the intended location of the new inlet works have commenced along the internal site road.

The Detritor has been isolated both from the wastewater flows and electrically, then cleaned, which has allowed our specialist sub-contract to come to site to remove the Detritor and take it off site for refurbishment, a process which will take some 8 weeks.

Electrical works have been carried out to remove lighting and instrumentation from the Distribution Chamber so that the structure can be repaired and reinforced, and the water containing areas can be fully waterproofed.

Installation of the new distribution arms to the rebuilt filters is planned for February, which, combined with other works, will allow us to circulate the flows through the rebuilt filters. Over a period of weeks this will cause the biological process to activate and bring the filters into operation.

Please note that the traffic management outside the site is not part of our works and is controlled by another contractor - emergency numbers should be displayed on the traffic management signage.

Thanks for taking the time to read the update. I have also attached photos to illustrate.

 

Dave Eden

Project Manager

Please Login in order to comment on this update.

Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers