Update by Geoff Joyce
Hi everyone
Latest update on Horsley WTW below:
Work has continued to wall construction to the Actiflo area at the north west corner of the site. Work continued also to the ground anchor installation at the south end of the site. It is hoped to complete this work tomorrow (Saturday) and to commence work on blinding concrete next week. See photos attached.
Some of the site team enjoyed a break from work on Wednesday, when they carried out some community work in Horsley village. A report on the work carried out will be published separately.
Have an enjoyable weekend.
Geoff