GENERAL PROJECT
CURRENT WEATHER
14°C

Horsley Water Treatment Works Upgrade

A £46M project to upgrade Horsley WTW has now reached a key milestone. We have selected our partner Mott MacDonald Bentley (MMB), to upgrade the treatment works.

Update by Shafqat Akbar

Hello. We achieved another one of our project milestones this week. We lifted the surge vessels into their final positions.

This crane lift was carried out in two phases. We lifted the vessels onto trailers and transported them to the second lifting location.

We lifted the 14 tonne vessels over a building and onto the reinforced concrete reception slab

The two vessels have been secured into their final positions. The mechanical and electrical fit-out will start later this week

 

Please Login in order to comment on this update.

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers