Update by Shafqat Akbar
In today's update I want to show you how much work is happening on this site. Here are some of the many work fronts that are currently open.
This is the first concrete pour for the passavant crane base.
The lamella structure in the sludge area has been positioned into it's permanent location. The fit out has started.
The scaffold enclosure to the HV swithroom is in place. Works inside this structure is ready to start.
The silos are ready to receive the first deliveries of chemicals.