Update by Shafqat Akbar
In this update, I want to share the good progress we are making on the mechanical, electrical and process installation. The site teams are working in a number of locations on site installing, testing and commissioning plant and equipment.
We have completed the installation of the chlorinated and unchlorinated tanks and booster sets.
We have received our first chemical deliveries of lime and PALC. We have completed the back washing of the filter beds at the rapid gravity filters. Progess has been very good.
The electrical testing is complete in many of the MCCs.
We have started the installation of the compressor and surge vessels at the pumping station. The MEICA works are progressing very well.