Update by Shafqat Akbar
Hello everyone. Hope you all had a lovely Christmas and New Year break. I want to update you about our return to work.
The site will work in line with the latest Covid restrictions issued by the Government on Monday 4th January 2021. We already have a safe system of work in place for these difficult times.
Site works restarted after the end of year break yesterday. We have an ambitious programme of works to deliver. The civils, MEICA and commissioning works have all restarted.
We are continuing with the hard landscaping works. This photo shows the new equipment that are being installed on the new concrete slabs south of the Rapid Gravity Filters.
The electrical and mechanical works are progressing well at serveral areas of the site. We will be testing the new installations shortly.
Please Login in order to comment on this update.