Work continues at pace on site at Horsley Water Treatment Works with good progress being made towards the commissioning of six new rapid gravity filters. The new dealkalizer plant is now fully operational and in service providing process water on site.
Our construction team continue with the site wide reinstatement including finishing works to new concrete footpaths and tarmac surface on the Spine Road. Other works include a gas main diversion to facilitate the next stages of work within the site.