Hi, everyone. Please find below a brief update on progress on Horsley WTW Upgrade scheme.
Mechanical installation has continued to the Actiflo building, and to the Rapid Gravity Filters.
Excavation for the Inlet Distribution Chamber has been completed and reinforcement and concrete works to the base slab were completed last week (w/e 24 Nov. '17).
The structural steel frame to the Chemical Building which will serve the chemical dosing to the actiflo streams has been erected.
Blinding concrete has been placed to the Birney Hill Pumping Station at the south end of the site. Reinforcement fixing has commenced to the base slab of thye pumping station.
Pipelaying to various areas of the site has continued.