Update by Julie Oakley
Dear Customer
We’re planning some further upgrading work in your area
I’m writing to you to let you know about the next phase of work we are planning to carry out at our treatment works at Horsley which will run from 2025 to 2027 and consist of three separate projects. This work is essential and represents a £33 million investment and will form part of the treatment process, ensuring the quality of the water supplied to 800,000 customers on Tyneside.
A new contact tank will be constructed in the South West of the works and will run from 2025 until late 2027.
Pumping station pipework renewal and commissioning of pumping station at the Southern end of the site which will run from April/May 2025 and last for around 12 months.
Construction of new chemical dosing facility which will include the construction of two number new coagulant tanks approximately 5 – 6 m in height to the North of the site adjacent to existing tanks that are larger in height. This is also due to run from April/May 2025 and last for around 12 months.
All the work will take place within and directly adjacent to our site boundary and will be undertaken by our supply partners Mott MacDonald Bentley (MMB) and Ross-Shire Engineering. We do not anticipate any disruption for you and, I just wanted to let you know that you may notice increased activity and more heavy vehicles movements from the site but with mitigation in place with vehicular movements avoiding the village, as well as a little more noise from the site.
The early phase of the enabling works for the Contact Tank work has commenced and will be limited to Monday to Friday, 8 am to 6 pm. We expect to complete our work by October 2027.
We are also planning a customer event so you can view and discuss our plans at Horsley Women’s Institute Village Hall on 04th March 2025 between 5.00 PM and 7.30 PM.
Please be assured that your water and wastewater services will not be interrupted while this work is in progress and, as with all work of this type, progress is subject to weather and site conditions.
Thank You
Julie