GENERAL PROJECT

Lanchester Sewer Treatment Works

As part of the Water Industry National Environmental Programme (WINEP), we will be installing chemical dosing plant (ferric sulphate and sodium hydroxide) and a new tertiary treatment stage to enable the site to meet the forthcoming phosphorous discharge consent. The improvement works will cost around £6.4m, and it’s one of 27 sites within the NWG region to receive this upgrade. Phosphorous is a nutrient and can cause algae to grow in watercourses, reducing biodiversity and river water quality.

Project updates

Update by Bethany Oakley

Good afternoon all,

Happy Wednesday!

I thought I'd jump on and update you on the recent progress that has been made on Site.

  • PS concreting works complete.
  • The concrete to the chemical dosing path is nearly complete.
  • The drain down pipework is also nearing completion.
  • Aquazone/Forbes Tanks now in place.
  • Intelect continue works and may take advantage of weekend working to continue with the great progress.

As always, if there is anything that we can assist with further, please don’t hesitate to reach out or add a comment in the box below and a member of the Project Team will respond accordingly.

Take care and speak soon,

Bethany

Please Login in order to comment on this update.

Update by Bethany Oakley

Good afternoon everyone,

I hope you’re well and keeping dry in this awful weather…

I wanted to share some information on the great progress that the Site Team have recently achieved.

  • The mecana slab and all associated pipework is now complete.
  • The denora is now complete minus the blower installation which we will be looking to complete on 14th October. We have also completed the ammonia sample chamber complete, minus the metal works.
  • Northern Power Grid completed some work on Site on 24th September.
  • NSAF pumping station is now underway and the DI pipework arrived on 24th September.
  • The Intelect works continue on site and the Mcerts tank and control panel delivered.

Thank you for your continued patience whilst we complete the required works and as always, should you like to ask us any questions or raise any concerns, please don’t hesitate to add a comment in the box below and a member of the Project Team will respond to you.

Take care

Bethany

Please Login in order to comment on this update.

Update by Bethany Oakley

Good afternoon everyone, happy Friday!

We wanted to keep you in the loop and let you know that currently we are in the busiest phase of the Project, but activity for large deliveries will subside in a few weeks’ time.

We will be updating you all with the latest progress very soon however in the meantime, should you have any questions please don't hesitate to add a comment in the box below and a member of the Project Team will be in touch.

Take care and enjoy your weekend.

Bethany

Please Login in order to comment on this update.

Update by Bethany Oakley

Good afternoon,

I hope you are well.

Since my last previous update last month, I have some further updates to share with you on the progress that has been made on the Treatment Works.

We have now built two out of three of the NSAF tanks and we have also got the new MCC cable trough completed. The third tank will be built following on from this and the new kiosk for the MCC will be on Site around 30th July.

We have also cleared the last of the reed bed and filled this with stone.

Should you have any questions to ask us, please don’t hesitate to add a comment in the box below and a member of the Project Team will respond.

Enjoy the rest of your week!

Bethany

Please Login in order to comment on this update.

Update by Bethany Oakley

Good afternoon, 

I'd like to start off the update by introducing myself, my name is Bethany Oakley and I am the Customer Liaison Officer looking after Lanchester Sewer Treatment Works on behalf of Mott Macdonald Bentley (MMB). Going forward I will be adding updates to the portal as the works progress. 

I will include some photos to my update for you to take a look at. 

Since our last update, I am pleased to report that the tankering operation has been complete however, the ecological visit for nesting birds is currently ongoing. 

We have also reclaimed a small portion of reed bed which will allow us to potentially start building the new MCC (motor control centre) trench.

The NSAF reinforcement is also coming together nicely and we have poured the second base slab for the chemical bunds. We are now continuing with the chemical bund walls.

Should you have any questions or queries, please dont hesitate to leave a comment below and a member of the project team will get back to you.

As always, thank you for your continued patience and cooperation.

Bethany

Please Login in order to comment on this update.

Update by Julie Oakley

Good afternoon,

I'd just like to start this update by introducing myself! My name is Julie Oakley, I am a Customer Liaison Officer for MMB taking over from Gaby and will be conducting the engagement with our customers and posting regular updates going forward!

Since our last update the final liqueurs return road crossing pipe have been installed to Caustic bund, the Chemical dosing area has been backfilled with the blinding timbers being erected for Caustic bund construction, the final prep works for caustic bund and shutters for concrete are underway and the removal of additional concrete from NPG duct excavation, additional concrete runs all the way through the chemical dosing area where ducts are to be installed

Keep a look out for more updates in the next month or so!

If you have any questions, please leave a comment below and a member of the project team will get back to you

Julie

Please Login in order to comment on this update.

Update by Gabrielle Ward

Good Morning,

It's been a while since our last post, so here's a quick update on whats been happening on site. 

The compound has now been fully setup and is in use. We have started works in the chemical dosing area that has consisted of exposing an old retaining wall and then breaking all of the concrete out form the wall and the base. The team have also constructed new and safe walk ways around the Sewage Treatment Works.

Keep a look out for more updates in the next month or so!

If you have any questions, please leave a comment below and a member of the project team will get back to you.

Gaby 

Please Login in order to comment on this update.

Update by Gabrielle Ward

Good afternoon,

Following on from Charles' update I thought I'd take this opportunity to introduce myself and some of the Mott MacDonald Bentley (MMB) team.

My name is Gaby Ward, I am the Customer Liaison Officer for Mott MacDonald Bentley (MMB) and will be conducting the engagement with our customers and posting regular updates on here. Working alongside myself at MMB is Jason Bradley, our Contracts Manager and Alex Brown our Site Agent. 

Over the next two weeks we will be starting to set up the site compound. Please be aware during this time, there will be an increase of vehicles accessing the STW delivering materials and the site cabins. If you are in this area, please take extra care. Once we have our working area set up, the volume of traffic will start to decrease and with our work being within the STW, any disruption should be minimal. 

The site will be closing down for the Christmas break from Wednesday 20th December until Tuesday 2nd January. 

On behalf of the project team, we hope you all have a wonderful Christmas and New Year!

Please Login in order to comment on this update.

Update by Charles Harman

I am Charles Harman, the Northumbrian Water Project Manager, and I will be looking after this project through to its completion. The project will be delivered by Northumbrian Water’s delivery partner Mott MacDonald Bentley. 

Starting in September 2023 we will be carrying out construction works at Lanchester sewage treatment works to add additional treatment processes to further improve the water quality of the Smallhope Burn, a tributary of the River Browney. The works should be completed by February 2025.

As the project develops we will keep you informed about our plans and progress by sharing our proposals with you on this portal. I am very interested to understand your views. 

The team will post regular updates throughout the construction phase of the project, and if you have any queries or want to make us aware of any additional assistance you require from us then please use the ‘Contact us’ button at the top of this page or post on this feed.

If you prefer a telephone conversation or require any further information or advice, please contact our Customer Centre on 0345 717 1100 or visit www.nwl.co.uk to request a call back from the project team.

Please Login in order to comment on this update.

Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers