Update by Julie Oakley
Good afternoon,
I'd just like to start this update by introducing myself! My name is Julie Oakley, I am a Customer Liaison Officer for MMB taking over from Gaby and will be conducting the engagement with our customers and posting regular updates going forward!
Since our last update the final liqueurs return road crossing pipe have been installed to Caustic bund, the Chemical dosing area has been backfilled with the blinding timbers being erected for Caustic bund construction, the final prep works for caustic bund and shutters for concrete are underway and the removal of additional concrete from NPG duct excavation, additional concrete runs all the way through the chemical dosing area where ducts are to be installed
Keep a look out for more updates in the next month or so!
If you have any questions, please leave a comment below and a member of the project team will get back to you
Julie