Update by Bethany Oakley
Good afternoon all,
Happy Wednesday!
I thought I'd jump on and update you on the recent progress that has been made on Site.
- PS concreting works complete.
- The concrete to the chemical dosing path is nearly complete.
- The drain down pipework is also nearing completion.
- Aquazone/Forbes Tanks now in place.
- Intelect continue works and may take advantage of weekend working to continue with the great progress.
As always, if there is anything that we can assist with further, please don’t hesitate to reach out or add a comment in the box below and a member of the Project Team will respond accordingly.
Take care and speak soon,
Bethany
Please Login in order to comment on this update.