Update by Bethany Oakley
Good morning everyone,
I hope you are all well
Before we leave for the Christmas Break, I wanted to provide a final update for 2024 and share some recent progress that the Site Team have continued to deliver, a great end to the Year!
- Flows now turned.
- NSAF seeding period started. (17th December)
- Overpumping is now in place for Mecana units.
- Aquazone commissioning complete this week.
- Intelect continue works, carrying on into the new year.
- Wash water booster set has been delivered to Site.
In the event that you require some assistance in our absence during the Christmas Break, please contact 0345 7171100.
Take care, have a wonderful Christmas and we wish you a happy and healthy 2025.
Speak next year!
Bethany