Update by Bethany Oakley
Good morning,
I hope you are well and are settling into 2025.
Since returning from the Christmas Break, the Site Team have continued progressing well with the Project, so I thought I’d share this with you.
- Ammonia sample point concrete shuttering and prep work.
- Road reinstatement prep work.
- NEPS installing pipe supports.
- Prep for MH28 to MH25 works.
- Intelect continue works.
- Concrete slots booked for every day next week. (Weather permitting).
As always, if you wanted to ask us anything, please don’t hesitate to add a comment in the box below and a member of the Project Team will respond accordingly.
Take care and speak soon,
Bethany