Update by Shafqat Akbar
The works at Lockwood Beck are progressing well but the weather will prevent us from finishing all of the works.
The installation of the tensar reinforcement on the embankment is almost complete.
The recent wet weather is has waterlogged the ground. We are not able to complete the construction on the top of the embankment in this site visit. We will agree a date for the return visit with Northumbrian Water.
The works at the bottom of the embankment will continue as these will not be affected by the waterlogged ground.
We have started installing the temporary works adjacent to the redundant Northumbrian Water buildings.
Please Login in order to comment on this update.