Update by Shafqat Akbar
Hello. Works at our Marden Quarry site are progressing well. We have a number of teams on site. In this update, I want to share the progress we are making on mechanical and electrical works.
We have replaced pump number 4 on site. The new pump installation is complete and the pump is operational. We are planning to replace pump number 3 next week.
The installation of the electrical MCC (control unit) is progressing well. The installation is about 50% complete.
The wiring and cabling works are progressing well. Our electricians are working in several locations.
The installation of the internal and external lighting is progressing very well.