Update by Shafqat Akbar
Hello again. I today's update, I want to share news on our site progress and give you some details about some of the works our site teams are carrying out.
We have agreed a programme of interventions with Northumbrian Water. This is where our site teams will connect new plant and equipment into the existing infrastructure.
For mechanical works, we have 4 interventions planned where our site teams will install new pumps in the main water pipe.
Our electricians have agreed details of 2 electrical tie-ins. These works will be carried out with close co-operation with Northumbrian Water staff to ensure all safety controls are agreed and in place before we start any works.
Our site teams are currently replacing 4 of the existing pumps, the mortor control centre (MCC) and the ventillation system. We are making good progress and are on target to achieve the next programme milestone.