Hello everyone. We have completed a lot of work at the Marden Quarry site since my last update. The works at Marden Quarry have progressed well over the past month. All four pumps have now been replaced and are operational, including the pipework and associated valves. The new electrical panel is installed and operational. The ventilation system has been replaced and is due to be commissioned in the next week.