Murton (Berwick) Water Treatment Works Upgrade

As part of our ongoing investment programme and to ensure the highest level of customer service, we are planning to extend and improve the existing Water Treatment Works at Murton, near Berwick. It is intended that the new works will be located adjacent to the existing buildings. The main construction work commenced in late 2018 and is due to complete in September 2020.

Update by Joan Tatters

Good Afternoon

A quick update, the mechanical and electrical installation within the Treatment building is ongoing and our subcontractor is continuing the cabling into the Pumping Station.

Pipetek are also battlling away with the pipework to both the east and west of the contact tank and even the fire alarm is being installed.

The weather has played a major part of our progress these past few weeks, even the signage on the fencing and at the entrance of the works has been damaged. Fencing along with sheeting have blown over.

The team are definitely being challenged with this weather!

Stay safe everyone!

Please Login in order to comment on this update.

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers