Update by Joan Tatters
Good Morning
This months' update..........
Treatment Building
The bulk tank and commissioning will commence later this month and the majority of the snagging works are complete within the building include the installation of the security system and fire protection system. All awaiting for the commissioning!
Filters1 & 2 are ready for painting, and 3 & 4 are complete.
Contact Tank
We are continuing to monitor the as it has now been filled.
Pumping Station
Installation of security system substantially complete as well as the fire protection system. The base of the kiosk sealed and grouted into position which doesn't sound much be believe you me it's a task.
WasteWater Settlement Tank
All the perimeter fencing installed with mesh infills are not quite done however the general pipework is done.
External Works
Concrete pours are complete around the Treatment Building with all road gullies installed to main access road ready for construction. Kerb lines currently being installed to access road ahead of macadam laying planned for next week and 2 commissioning cabins have now been removed from site and the area returned to car parking space.
That's a brief over view of where we are and giving the weather has been so variable I think the team are doing a great job.
.