Killingworth Road - wall repair

We are working hard to repair the wall on Killingworth Road - we will use this page to provide updates about the repair and also the work required to clean up and reinstate the affected area.

Update by Christine Taylor

Good afternoon,

Following my update last week, with regards to a case of Covid on site.  We are now in a position to confirm that we are unable to replace this key member of the team this week.  This means our piling work is on hold until Monday13 September 2021.  Our site team will be reduced this week, until piling restarts next week.

Please accept our apologies, as we follow government guidelines we appreciate your understanding.

Our progress on site last week;

  • Roger Bulivant (pilers) pile casing installation - 45% complete as of Friday
  • The Pilers encountered the rock strata at a higher level, slowing progress due to hard ground
  • ESH ops continuing to clear arisings from pile operation.
  • Access and tightness of site, continuing to restrict progress

Christine

Please Login in order to comment on this update.

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers