Update by Christine Taylor
Good afternoon,
Following my update last week, with regards to a case of Covid on site. We are now in a position to confirm that we are unable to replace this key member of the team this week. This means our piling work is on hold until Monday13 September 2021. Our site team will be reduced this week, until piling restarts next week.
Please accept our apologies, as we follow government guidelines we appreciate your understanding.
Our progress on site last week;
- Roger Bulivant (pilers) pile casing installation - 45% complete as of Friday
- The Pilers encountered the rock strata at a higher level, slowing progress due to hard ground
- ESH ops continuing to clear arisings from pile operation.
- Access and tightness of site, continuing to restrict progress
Christine