GENERAL PROJECT

Killingworth Road - wall repair

We are working hard to repair the wall on Killingworth Road - we will use this page to provide updates about the repair and also the work required to clean up and reinstate the affected area.

Project updates

Update by Christine Taylor

Good morning,

This is a great day for the residents of the area, this is our farewell post as we have now completed all our works and removed our compound.  The compound area has been cleared, levelled and top soiled.  Our old site entrance has been reinstated back to the existing footpath.

We will have landscapers in the area in the next few weeks, so I will still be here, on the portal watching to ensure our customers remain happy.  Later this year, once the Environment Agency has completed works in the watercourse, we will send a team to remove our sedimats under the fall tree.  Do not hestiate to contact me if you have any questions or concerns over the next few months.

Me and Adam would like to personally thank all residents for their patience throughout the works.

Have a great weekend and a wonderful Jubilee celebration next week.

Christine and Adam

Please Login in order to comment on this update.

Update by Christine Taylor

Good evening,

As we come closer to our departure from site, our site team have provided a further update of our progress.

This week the team have;

  • Finished construction work on site in the rear lane of Killingworth Road last week of April
  • Carried out conditional CCTV survey check of existing sewer to rear lane, awaiting reports
  • New wall to rear lane cleaned off
  • Commence demobilisation of site compound, including removal of site cabins and hard standing
  • Topsoil reinstatements to compound ongoing

Planned works for next week:

  • Reinstate Kerbs and footpath to site compound entrance
  • Remove all remaining fencing and materials from site compound by end of the week

As always we thank you all for your continued patience whilst we complete our works in the area.

Christine

Please Login in order to comment on this update.

Update by Christine Taylor

Good morning,

I hope everyone had a lovely Bank Holiday weekend?

As we posted on Friday, the main work in the back lane is completed and it is now re-open.  This week Adam will be organising for the wall to be cleaned off, this is currently planned for Thursday.  CCTV of the sewer will also be taking place this week.

Over the next couple of weeks, the team will be starting works to reinstate the compound area on the the junction of Salters Bridge and Killingworth Road.

Whilst we are in the area, we will continue to provide updates.

Thank you for your continued patience and understanding.

Christine

Please Login in order to comment on this update.

Update by Christine Taylor

Great news!

As you can see the back lane is now open and ready to use. Adam has asked that customers don't park on it until after 6pm as the tarmac is still soft.

Have a wonderful bank holiday.

Christine

Please Login in order to comment on this update.

Update by Christine Taylor

Good afternoon,

It's great news!

Our work is close to completion in the back lane.  We are expecting the tarmac on Thursday and Friday, and then the lane will be open.

Next week, our supply partners Pipetek will be carrying out CCTV and a further contractor jetwashing the wall. The lane will remain open whilst these works are completed.

Tomorrow our customers will not see our crews, as they are working in the main compound whilst we wait for the tarmac.

Thank you for your continued patience.

Christine

Please Login in order to comment on this update.

Update by Christine Taylor

Good afternoon,

As our works come closer to completion to the rear of the properties, please see below provided by Adam.

Progress this week:

  • Installation of kerb line and gully to back lane completed early this week
  • Stone up and compaction of narrow path and road completed
  • Reinstatement of Aco drainage units completed
  • Alter site fencing in prep for tarmac reinstatements next week

Planned works for next week:

  • Pour narrow concrete footpath to rear of new wall to be complete early next week
  • General tidy up and prep for tarmac reinstatements
  • Reinstate road surface to back lane, to be completed late next week

We hope you all have a great weekend.

Christine and the site team

Please Login in order to comment on this update.

Update by Christine Taylor

Good afternoon,

As we all prepare for the Easter break, Adam has sent over his usual update.

Progress this week:

  • Coffer dam removal completed earlier this week.
  • Gully base and pipework installed, building up to finished road level to be complete by early next week.
  • Commence install of kerbs to narrow foot path of rear of new parapet wall. Expected to be completed by early next week.

Planned works for next week:

  • Complete Kerbs to narrow footpath.
  • Stone up and prep ready for tarmac road reinstatements.
  • Stone up and prep for reinstatment of narrow concrete footpath to rear of the new wall.
  • Lay concrete to reinstate narrow path at rear of new parapet wall.

Me and the team would like to wish you all a great bank holiday, and I hope the sun comes out to join us all.

Christine

Please Login in order to comment on this update.

Update by Christine Taylor

Good morning,

Sorry for the late update.  

This week the team continued with removal of coffer dam from the Ouseburn watercourse. These works have been hampered by the weather and high river levels.

Planned works for next week:

  • Complete removal of the coffer dam from the Ouseburn.
  • Commence works to reinstating the back lane, starting with the installation of the gully, followed by installing kerbs to narrow footpath at rear of the new wall.

Have a lovely weekend.

Christine and the team

Please Login in order to comment on this update.

Update by Becky Gartland

Good afternoon, 

The weather has certainly been very different this week, compared to last, as you'll see from Adam's photo's attached. The site team however have remained positive and have still managed to progress with the works as detailed below:

Progress this week:

Additional silt protection measures installed on Monday, due to the fallen tree in the Ouseburn watercourse covering existing silt protection measures.

Commence removal of coffer dam to the watercourse.

Removal of the coffer dam being hampered by rain and snow, causing high water levels to the river.

Planned works for next week:

Continue with the removal of the coffer dam from the river.

The pumping tank is being removed from site on Monday, late morning. If we could continue to ask residents not to park in the back lane during working hours.

If you have any queries at all, please get in touch with us. 

Regards 

Becky 

 

Please Login in order to comment on this update.

Update by Becky Gartland

Good afternoon everyone, 

I hope you have all been enjoyiong the lovely weather we have had this week!

Adam has very kindly provided me with your weekly update on what work has been completed and what you can expect for next week:

Progress this week:

  • Replacement of the land drain to rear of new wall completed early this week.
  • Commence with stone up and prep work to allow removal of coffer dam from within the Ouseburn watercourse.  

Planned works for next week:

  • Complete coffer dam removal prep works.
  • Commence removal of coffer dam from the watercourse.

If you have any queries, please let me know. 

Have a lovely weekend!

Becky 

 

Please Login in order to comment on this update.

Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers