Update by Christine Taylor

Good morning,

Please see our progress this week:

  • Completed the remedial works following various flood events during December
  • Commence drilling of the piles for the dowels, to tie the new toe beam to the piles

Next week the crew into to: 

  • Continue with brickwork demolition for remedial works to the south end of our works
  • The team will continue drilling of the piles for the dowels, to tie the new toe beam to the piles
  • Commence rebar cage construction and installation, with concrete of beam to follow

Have a lovely weekend.

Christine

Please Login in order to comment on this update.

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers