Update by Joan Tatters
Good Morning All,
It's been a while since our last up date so we thought it's about time you were made aware of the progress.
Since Christmas we have made good progress despite the weather. The main structure is now complete and has been fitted out with the pipework, cabling and the media required to run the treatment process. At present the new structure is going through the commissioning stage and shortly the new process will run fully automatically . Around the new structure itself we are completing the reinstatement works, installing footpaths and tying in to the existing levels .
The second stage of our works on site is expected to start this week, however the weather will play a big part in that decison as we plan to start work to construct a New Primary Settlement Tank near the existing inlet works
Please stay safe and warm during this weather and if you want to ask us any questions please feel free.