GENERAL PROJECT

Pegswood

Together with our supply partner, Mott MacDonald Bentley, we plan to carry out over £3 million of investment work to upgrade the sewage treatment works to improve the quality of the Bothal Burn for the benefit of the people, environment and wildlife.

Start Date

May, 2017

Estimated End Date

March, 2019

Contractor

NW, Mott MacDonald Bentley

Update by Joan Tatters

Good Afternoon

This weeks update.................Paul and the guys have now completed the installation of the precast structure which was a job and a half due to the scale of th operation.

The precast structure up to 7m high totalling 500ton were lifted by a 100ton crane into the correct place with precision. The crane towered the site and during the forthcoming weeks the floors and the walls will also be cast.

Paul has sent me some photos

Please Login in order to comment on this update.

View all updates
Rate us

Rate us

We would love to hear your feed back on our community portal.

There was an error saving your answers. Please try again.

Saving your answers.
Please wait.

Your answers have been saved. Thankyou for giving us your feedback.

1. Do you feel that our Community Portal has helped to keep you informed about our work?

2. How likely is it that you would recommend our Community Portal to a friend or colleague?

3. How likely is it that you would recommend Northumbrian Water to a friend or colleague?

4. Do you have any suggestions to improve our Community Portal? Optional