Update by Jane Cooper
Hello,
Sacriston is substantially complete now with only some minor mechanical and electrical works ongoing to get us to completion.
Back in December we finished commissioning the new chemical dosing systems and the cloth filter mecana unit. Dosing then also commenced in December, and we are now in a period of testing and sampling on site to ensure the final water quality meets the new consent levels, this process usually takes 2-3 months to complete.