The construction phase of this project is now complete.

There may still be updates, so the project will remain here. We are still monitoring the project and will reply to any comments. So if you have any questions please feel free to comment or contact us here.

GENERAL PROJECT

Sacriston Sewage Treatment Works Upgrade

We are investing over £3 million to improve the performance of our wastewater treatment at Sacriston. This essential work will help to improve the water quality of the South Burn for the benefit of people, the environment and wildlife and ensure that the treatment facility continues to serve the community effectively.

Update by Jane Cooper

Hello, 

Civil works is now nearing completion on site at Sacriston, with the new delivery road complete and the sludge tank installed and awaiting connection to go into service.

We’ll now be concentrating on finishing the remaining small amount of civil works, and then the mechanical and electrical installations can begin.

In the next two months or so we will look to start the commissioning process for the new works.

Please Login in order to comment on this update.

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers