Update by Jane Cooper
Hello,
Civil works is now nearing completion on site at Sacriston, with the new delivery road complete and the sludge tank installed and awaiting connection to go into service.
We’ll now be concentrating on finishing the remaining small amount of civil works, and then the mechanical and electrical installations can begin.
In the next two months or so we will look to start the commissioning process for the new works.