Hello,
The civil works on site are now substantially complete for all the process installations, and final minor civil works should be completed by the end of January 2025.
Mechanical and electrical installations are nearing completion and the works is now dosing chemicals into supply, with sampling and monitoring for the Environmental Agency ongoing.
Works will continue into early 2025 but with substantially reduced activity on site.