Good morning,
I have a quick update from our site team of how they are progressing. Ian has also sent some photos of the Dam’s Sloping Pitching works area.
ESH Stantec have appointed a specialist subcontractor Hesselberg Hydro, who are continuing with the installation of OSA (Open Stone Asphalt) to sloping pitching of Selset Reservoir Dam. They are continuing with the laying off a 175mm thickness of OSA material working North- South along the Dam Revetment Area.
The team are confident by this evening that nearly half of the surfacing repairs will be complete.
Have a lovely weekend.
Christine