Update by Brian Hall
Hello everyone
We have just about finished work now at Thorpe with just a few minor items to sort out inside the building. We will shortly be removing our cabins from the site and returning everything to normal. We will be relocating then to Fulwell Ground Water Station to commence work later this week. These works will last until around the end of November. The project involves installing new filters and pipework along with amendments to the pumping arrangements to provide improvements to water quality and the environment.You may notice an increase in traffic but we will try to keep disruption to a minimum. Our hours of work at 8am to 5pm Monday to Friday and if we work outside these hours we will inform you in advance. Water supply will be unaffected.
Best regards
Brian