The Grove, Coxhoe

Working with our supply partners, Mott MacDonald Bentley (MMB), we are investing £130,000 to improve the sewerage network serving your local area.

Update by Sarah Jayne Parvin

Good afternoon Residents! The site compound, as you will have seen is all set up.

Trench works and Chamber positions set out, and on Friday the ground around the man hole,  OS 15 The Grove was cut and we are under way with excavating this section of the works.

We woluld like to thank everyone for your patience and understading. If there are any proplems please dont hesitate to contact us using the comments function below, Likewise if you have any positive feedback i would love to hear that!

Thanks 

Sarah 

 

 

Please Login in order to comment on this update.

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers