Update by Dave Eden
Morning all,
Work is continuing at Pipeline Management in Windmill Hills park, but we are starting to reach the pointy end.
The pipework alterations have all been carried out the larger of the two water mains, including installation of the 600mm diameter Electrically Operated Valve (EOV), and that is now back in service.
The flow control chamber is about 75% complete. We’ve left a section out to let us carry out the alterations on the second water main and we have the precast concrete cover slab to go on at the end of this month.
We are currently carrying out some ductworks to allow the M&E installation to start in the next 2 weeks and we’re working with NWG to isolate and drain the second main so we can carry out those adjustments mentioned above next week.
Thanks
Dave