Update by Bethany Oakley
Hi all, I hope you're well.
Following the previous updates, I am delighted to let you know that we have a date for the works to commence.
We will be starting works on 11 November 2024 for approximately 4 months. Works will be starting with the creation of the site compound which will be located in the Church Hall car park on Valley Gardens.
Following this we will begin to install traffic management on Cutlers Hall Road on 18 November 2024 until we move to Valley Gardens in January 2025.
During the work on Valley Gardens there will be no access for vehicles in the working area, however pedestrian access will remain open. However, to be clear we will be working at the bottom of Valley Gardens in 2 sections throughout the duration of the 4-week period which will end on 28 February 2025. This is to help minimise disruption as much as possible.
As with all construction projects, unexpected delays can sometimes occur. Please be assured that we’re working closely with our partners to do all we can to minimise any disruption for you and your community throughout the work. Typical working hours will be between 8.00am to 4.00pm, Monday to Friday.
If you have any questions regarding the above or any general queries, please don't hesitate to add a comment in the box below and a member of the Project Team will respond.
Thank you,
Bethany