Update by Joan Tatters
Good Afternoon,
Firstly I am sorry I didn't get up to see you this morning, normal service will resume next week.
Top Site
The earthwork and the lagoons are almost complete however some of the excavated material is unsuitable for recycling into the lagoons and we have had to remove it off site.
The Pumping Station
The pumping station shaft segments have all been installed and have been sealed and at long last and we are pleased to say only took 4 days to build however, substantially longer to blast. The shaft framework is progressing and we are due to start the valve chamber construction and we intend to build above the rock level.
River crossing
The tie in works are unfortunately in rock so we are continuing to explore an alternative method to blasting to complete the works.
Drainage to the Mill area
Unfortuntately this area has been used in the past as a tip and we have uncoverd various materials. We would have normally used this material to backfill however, I'm afraid not on this occasion. For the historians..........apparently this area was an old historic dock.
Main drainage to the highway
We are still encountering rock which has stumped the experts, we are now employing an non explosive means of removal in this area. We have rock at one end and bad running sand at the other with water ingress.... such joy!
The work on the manhole and the outfall continues, once again the outfall is again in rock (no news there)
Well that's it from me today, hope to see/speak to you next week. In the meanwhile please drop me a line if you need to ask anything.
PS, more photos!
Please Login in order to comment on this update.