Update by Joan Tatters
Good Morning,
It's been a while, I thought I'd let you know I will be dropping in some letters to residents Tuesday morning.
As you know, we have now successfully completed the new sewerage works in the village and this has been up and running since Autumn 2019.
We will be returning during week commencing 6 July 2020 to complete localised stabilisation of the riverbank in the vicinity of the pumping station. We will be placing large boulders along a 22m section of the river bank, on either side of the concrete outfall and completing some outstanding reinstatement.
It is anticipated these works will be completed within four weeks and there should not be any direct inconvenience to local residents.
If you have any further questions please do not hesitate to contact me.
Please Login in order to comment on this update.