Update by Sarah Jayne Parvin
Good afternoon, we want to make you aware that we will be doing the second concrete pour on Thursday, 13th May.
We are pouring the second floor of the three Final Settlement Tanks, placing 170m3 concrete to form the base. We still have one more to complete and will notify you ahead of the work.
We expect the shift to run into the night as the concrete needs to set to a point where it can be walked on, and power floated to give a smooth finish. There will be some low-level lighting equipment on-site that provide safe access/egress to the works area and noise when the power float is used throughout the shift. I have included some pictures below of the last concrete pour.
You can comment below or use the ‘contact us’ option above to speak to one of the team.
Thank you for your patience during this time.
Sarah