Update by Sarah Jayne Parvin
Good afternoon,
We want to let you know we have a further concrete pour to do tomorrow.
The concrete pour is for the Ballest ring, which in easy terms, is a concrete ring poured to seal the walls, to the base of the tanks. To form the ring a 165m3 of concrete needs to be poured. It is programmed to start on-site at 6 am setting up the concrete pump, and the concrete wagons will start coming into the site from 7 am. We are hoping to be finished by 4 pm. However, there is a chance this could run on a bit longer. Other than the wagons in and out of the site, we don't expect any further disruption.
Any questions, don't hesitate to comment below.
Thanks
Sarah