Update by Julie Oakley
Good afternoon,
I hope you all have had a lovely Christmas and a Happy New Year
I would just like to provide you with an update on the project here at West Hallington, we have made good progress after the Christmas break and we are on with the dry comissioning, as most of you are aware we have the wet comissioning of the siphon coming up, we now have the dates for this which are Monday 22nd January 2024 and then again on Thursday 25th January 2024, we are not anticipating any major disruptions, as a precuation you will see temporary traffic lights on the side of the road but these will only be used if neccessary.
In the meantime if you have any issues or concerns please do not hesitate in leaving a comment below or contacting myself.
Many thanks
Julie